From Monday 18 April contractors will be installing two raised platforms along Vogel Street, Cambridge to encourage drivers to travel slower and improve pedestrian safety and accessibility - the works will take 4 weeks. Stop and go signs will be in place for the duration of the works, with temporary road closures at times while the raised platforms are being constructed. We will ensure residents have access to their driveways and will keep delays to a minimum. We would like to thank you for your patience and understanding while we upgrade the street for our community.
- Stop and go signs will be in place for the duration of the works, with temporary road closures at times while the raised platforms are being constructed.
- Residents have been notified, have access to their driveways and will ensure we keep delays to a minimum.
- Work will take place between the hours of 7am - 5pm with the road reopening at 7pm on weekdays and 8am - 4pm on Saturdays. There will be construction noises and slight vibrations throughout these hours.