Cambridge Water Tower
How much does it cost to prepare a consent application and what is involved in it?
It varies on a case-by-case basis – it is not a definitive process. It involves preparing an assessment of environmental effects, establishing a portfolio of technical evidence, evaluation of options, consultation, lodging the application, presenting to a consent hearing, meeting the costs of the hearing, and repeating the application process if the consent decision is referred to the Environment Court.
What is the consent fee?
The final consent fees won’t be determined until the consent decision has been issued. It depends on the amount of time required to process the application, the actual hearing costs and processing the consent decision.
How much is the demolition cost?
Our preliminary estimate of the demolition costs is approximately $300k for budgeting purposes.
How much will the commemorative structure cost and who was contacted for that?
The commemorative structure is only a suggestion at this stage. If the tower was removed, we have mooted the idea of retaining some sort of commemorative structure at the site but have not advanced any detailed design on that concept. There will be other parties who may wish to have input into developing that idea.
What are our options?
There are two key options for the future of the water tower – remove or restore. Doing nothing is not an option due to the unsafe state the tower is in. Council did consider relocation, but the process and costs involved means this option simply isn’t viable.
Are there alternative uses for the Water Tower in the event it would be retained or restored?
During consultation on Council’s draft 2024/2025 Enhanced Annual Plan, some submitters mentioned possible alternative uses for the water tower. These included a library, viewing platform. etc.
The water tower is located on recreation reserve and is the subject to the Reserves Act 1977 and Section 11 Waikato Raupatu Claims Settlement Act 1995. Alternative uses proposed for the water tower would be subject to the restrictions that would need to be met under the relevant legislation and regulations.
What are safety concerns with the structure?
The Cambridge Water Tower has been assessed as earthquake prone. In addition, there are some other risks associated with badly corroded steel work attaching to the water tank and tower that pose a safety risk if they fall.
Is it correct the council is in the process of seeking a demolition consent? What does that involve?
That is correct. The consent application will follow standard procedures and will be required before any work (demolition or strengthening) takes place.
It will involve preparation of detailed information that supports the application including engineering reports, an assessment of environmental effects, and consideration of options. The application will be considered by a hearing committee and will be subject to submissions.
While an application for a resource consent for demolition was progressing, Council would keep an open mind to alternatives.
Less than two years ago Council said in a press release the structure was heritage listed and could not be demolished? What has changed?
The structure is a Category 2 Heritage Building registered by HNZPT. That means that we can’t do work on the building other than maintenance without a resource consent. If Council is not granted a resource consent, the tower will not be able to be demolished.
Did Council go out for public consultation on this issue in May?
Yes as part of the 2024/2025 Enhanced Annual Plan, 223 submissions were received. 62% in favour of removing the tower, 38% wishing to restore the tower.
Will Council wait and see what comes out of central government’s relook at earthquake strengthening rules?
What is the timeframe for the water tower demolition process? What are the next steps?
The timeframe is dependent on the outcome of the consent programme. We are only in the early stages of that given the 2024/25 Enhanced Annual Plan took effect on 1 July 2024. The consent process will extend into 2025.