Building a small stand-alone dwelling (granny flat)
What is a granny flat?
To be eligible for this exemption, a granny flat is a new, stand-alone home for one household. It must be no bigger than 70 square metres and have only one storey. It must be at least two metres from boundaries and other homes.
The floor can be no more than one metre above the ground. The total height must not be more than four metres.
It cannot be an addition to an existing building or a conversion of something that is already there.
What does the Building Code require?
| Water and drainage | If council water and wastewater services are available and
have space, the granny flat must connect to them.
If a connection is not possible, an on-site system can be used instead. This could be an existing system or a new one. If an on-site system is added or changed under this exemption, you do not need a building consent. You may still need a resource consent. |
| Power, gas and heating | The granny flat must have its own electricity supply. If gas
is used, it must also have its own gas connection.
Any heating must be electric or gas. Wood burners and other solid fuel heaters are not covered by this exemption and will need a building consent. |
| Showers | Granny flats can include simple, ready-made shower units. They cannot include level-entry or wet-floor showers. |
| Natural hazards | If the site is affected by flooding, slips, or
other natural hazards – or if the build could make these worse – steps must be
taken to protect the land, the building, and nearby property.
If this protection cannot be provided, you cannot use this exemption. A building consent will be needed, and a note may be added to the property title. |
Can I build a granny flat myself?
Only if you are, or are working under, a licensed building professional. Most homeowners cannot legally design or build a granny flat on their own.
Licensed professionals include builders and designers who are Licensed Building Practitioners, as well as licensed plumbers, drainlayers, gasfitters and electricians.
What happens if I don’t follow the rules?
If you do not meet the conditions, there can be serious results. You may be fined, face legal action, or have trouble getting insurance. You may also need to redo work or apply for consents you thought you did not need.
You can be fined if you do not send the required documents within 20 working days, if you build without a consent when one is needed, or if you create a building that is unsafe or unhealthy.
Council can issue a Notice to Fix if the build does not meet the rules, does not meet the Building Code, required documents are missing, or the building is unsafe.
Homeowners and building professionals must understand their responsibilities and make sure every requirement is met.